News

Giant new defence fulfilment centre handed over for the MoD

Knight Webb have confirmed the successfully completion and handover on programme and within budget of a giant new 850,000 sq ft warehouse development constructed for Kuehne + Nagel in Donnington, Shropshire

The complex project was completed on behalf of Leidos and The Ministry of Defence (MoD) and involved the integration of a fully automated mini-load storage/retrieval system.

The project which involved the sub-division of each building into separate 4 hour fire chambers required a detailed fire engineering solution to be agreed with the Insurers, Approved Inspector and End Users.

Commenting on the project Knight Webb Director and Co-founder Paul Knight said: “Knight Webb have been involved in the development and delivery of this project from first inception.  This has been a fully integrated project with the design team working closely with the end user, Planning Authority and Approved Inspector in order to achieve an effective solution.  We are delighted with the outcome which is one of the largest build to suit warehouse development projects we have been involved in to date”.

More News

Well deserved Promotion

Stephen Baldwin promoted to Associate Director

Successful completion for Segro at Hayes

Another completion at SEGRO Park Hayes

New appointment with Segro and DHL in Coventry

Strengthening of the partnership between Segro and DHL

Featured Project

1 Million Square Feet for MOD, Donnington

Construction of three buildings totalling 1 million square feet for the MOD in Donnington, Shropshire.

Featured News

Well deserved Promotion

Enquire Now

Stay in touch

Please feel free to contact us about any enquiries you may have.

Our Customers